What did commissioners decide on November 12?
The county’s project update says commissioners approved the Data Center Interim Zoning study at their November 12 public hearing. It says staff were directed to begin the study’s recommended work, including developing regulations and coordinating with other governments.
Official sources: County project update and timeline
Did that decision adopt permanent zoning rules?
Study approval is not the same as adopting permanent data-center zoning. The November 12 update directs staff to develop countywide rules but does not announce a completed ordinance or new final regulatory text. The county’s FAQ says existing regulations already cover data centers; those are separate from the updates now being developed.
Official sources: County project update and timeline · County data-center project FAQs
Why does the county’s timetable extend into 2027?
The update places completion of the regulations after the 2027 Montana Legislative Session so staff can account for any statutory changes. It supplies no specific day for final adoption or a new hearing.
Official sources: County project update and timeline
What temporary restriction does the county describe?
Its project page describes a one-year moratorium on new or expanded data centers outside city limits. The page lists July 8, 2027, as its expiration date unless new zoning replaces it earlier. It says an additional year would require another advertised public hearing rather than an automatic extension.
Official sources: County project update and timeline · County data-center project FAQs
Does the update announce a change to electric bills?
The county says it will continue participating in NorthWestern Energy’s Large New Load Tariff proceeding before the Montana Public Service Commission. The update describes customer protection as a goal, not a promised reduction in bills.
Official sources: County project update and timeline
Where can residents follow the next steps?
The county’s project page carries the November 12 update, study-document links and a separate FAQ section. Its earlier meeting notice still lists the November 12 hearing, which should no longer be read as an upcoming event.
Official sources: County project update and timeline · Original county meeting notice