Honolulu has changed both the start date and traffic plan for repairs to a collapsed underground drain near Magellan Avenue. The city’s October 19 notice supersedes a September announcement that set an October 12 start and a continuous road closure.
The affected stretch runs between Miller and Alapaʻi streets. Residents can still reach their properties, and the contractor will coordinate deliveries, refuse collection and emergency access. TheBus Route 122 will keep its usual route.
Parking in front of Dole Community Park remains prohibited while the project uses the area for equipment and materials. Through drivers should consult the city’s published eastbound and westbound detours.
The original notice estimated four months of work. The amendment does not give a revised completion date. Project questions go to the Department of Design and Construction at 808-768-8400.