Honolulu plans to start rebuilding a stretch of Kapiʻolani Boulevard on November 16, bringing lane restrictions to the corridor between Ward Avenue and Atkinson Drive. The Department of Design and Construction announced the project November 6 and estimates about 18 months of work.
The city awarded the $9.9 million contract to Hiʻilawe Construction, LLC. Crews will replace the asphalt and work on sidewalks, curbs and gutters. The scope also includes utility-cover adjustments, vehicle-detection loops, road markings and signs; trees and roots may be trimmed or removed where necessary.
The announced daytime schedule is 8:30 a.m. to 3:30 p.m. on weekdays, with holidays excluded. Some later phases may involve overnight work, but the notice does not provide a nighttime timetable.
Lane restrictions will vary with the work underway. The contractor is to maintain at least one traffic lane in each direction throughout the project, rather than close the road completely. The city warns of possible delays; it has not supplied a day-by-day closure schedule.
The department lists 808-768-8400 for project questions and comments. Its November 6 correction removed traffic-signal installation from the release; that activity is not part of the scope described here. The 18-month duration remains an estimate, not a confirmed completion date.