What bridge is being considered for replacement?
The proposal concerns Bridge No. 01012, which carries Route 49, also called Ekonk Hill Road, over the Pachaug River in Voluntown. CTDOT’s current project page describes deterioration in the concrete tee-beams and says the replacement would bring the structure up to current roadway standards. This is the department’s project assessment, not an independent engineering inspection by State & Nation.
Is the public meeting still ahead?
No. CTDOT now lists the November 3, 2026, virtual meeting as held and links its recording and meeting report. The report records a start at approximately 6 p.m.; neither it nor the original meeting notice specifies a time zone. The announced November 17 comment deadline has also passed, and the current project page still lists that date rather than a new comment window.
How much would the work cost?
CTDOT’s current project webpage lists an estimated construction cost of $7 million and an anticipated funding split of 80 percent federal funds and 20 percent state funds. The meeting report separately gives an estimated total project cost of approximately $6.9 million. These are the figures in the two agency documents, not final bids or confirmation that funding has been secured.
When could construction begin?
The project webpage anticipates a spring 2029 start, depending on funding, property acquisition and permits. The meeting report describes a spring or summer 2029 start and work within a single construction season, subject to available funds. Neither document establishes that construction has started or supplies a guaranteed opening date.
What traffic changes are proposed?
The meeting report describes an approximately 11-week Route 49 closure during summer 2029. Its proposed detour uses Routes 138 and 201, Route 395 and Route 14A before returning to Route 49, with an estimated distance of 23.2 miles and travel time of 30 minutes. Those are planning estimates, not an announcement that the road is closed now or that an individual trip will take exactly 30 minutes.
Where are the project records and contact details?
CTDOT’s project page links the presentation, location map, public notice, project description, meeting report and recording. It lists DOTProject147-63@ct.gov and project manager Kevin Blasi as contacts, with State Project No. 0147-0063 used to identify the proposal. The links provide access to the agency’s records; they do not themselves establish a final construction authorization.